Big news! Drum-roll… We received our occupancy permit. The kids are in!

Take a look at this gorgeous space. A huge thank you to Micah and Philippe for making it happen with such vision, artistry, and hard work, and to everyone else who contributed time and energy, and believed it could be done.

Progress made last week:

  • floor installation was completed.
  • light fixtures were installed.
  • a section of the foyer roof over the entrance, bathrooms and faculty room was built. 

Building continues on the connecting corridor and faculty room.

Work scheduled for this week:

  • complete the ICF walls and roof in the prep kitchen area.
  • fill the ICF walls with concrete.

Help is always much appreciated. Contact Micah, at 1micah@gmail.com, if you can volunteer.